August 4, 2026

PSO parent company, AEP, moves to meet increased energy demands

As the American Electric Power, parent company of Public Service Company of Oklahoma, sees an increase in contracted data center and large industrial load pipeline, it also has made a concerted effort to secure more gas turbine capacity to meet the demand.

As Utility Dive reported this week, AEP secured 3 GW of capacity in the second quarter and now its total turbine supply that can be deployed by 2031 will be about 13 GW. The declaration came from Bill Fehrman, AEP chairman, president and CEO.

PSO is among AEP subsidiaries that are dealing with increased pressures to meet the surging demand for electrical powers and like other AEP firms, it is faced with such large-load requests from proposed data centers and a $4 billion aluminum smelter in Inola.

Large load pipeline grows

AEP’s contracted large load pipeline grew to 69 GW, up from 63 GW in the first quarter, according to Mihalik, reported Utility Dive.

The data center and other large load pipeline includes 45 GW in Texas, 12 GW in Ohio, and Oklahoma, Indiana, Kentucky, Louisiana and Virginia combining for 12 GW, he said.

AEP utilities’ large load tariffs require customers to make long-term commitments and support the investments needed to serve them, Mihalik said.

“These tariff frameworks also provide strong protections against project delays and changing development timelines, giving us confidence that we can capture this growth while appropriately managing potential risk,” he said.

The acquisition of new gas generators is critical to AEP’s efforts to meet the electrical power demands in the states where the subsidiaries are located. It also shows the difficulty in obtaining such costly power generators.

“The new generation investments are going to play a pretty central role in driving the long-term growth as we look to deploy this 13 GW of turbine capacity across the regulated businesses,” Fehrman said.

Turbines are “a scarce resource and will become increasingly more valuable,” he said. “We’re going to continue to be aggressive in our positions on this, and we’re continuing to actively work with the key suppliers and are very confident that not only with what we have locked up, but we’ve got clear line of sight through certain framework agreements and such that we can get what we need to continue to deliver for customers.”

AEP also is making acquisitions elsewhere to meet the power demands including a deal to buy a coal-fired power plant near Maidsville, West Virginia, as reported by the Financial Times reported last week. The Columbus, Ohio-based utility company also bought a permit to build a 1.2-GW gas-fired power plant at the same site in Maidsville, West Virginia, the paper said.

AEP’s utilities expect to add 27.2 GW to their systems by 2035, according to the company’s earnings presentation. Their resource plans call for adding: 15.3 GW of gas; 6.4 GW of solar; 5.1 GW of wind; and 500 MW of storage. The utilities have pending requests for proposals totaling 7.8GW, according to the presentation.

AEP finished the second quarter with a decline in income of $713 million, down from $1.2 billion in the same period a year ago. The drop in income came as AEP experienced an increase in its commercial and industrial sales in the first six months of 2026.

 