Data center development remains in the headlines, whether it’s the effort of energy utilities and firms to meet the demand for AI and electricity needs or whether residents of cities and towns fight the projects.
A review of some recent developments includes Yukon, Oklahoma where the residents fought a proposed data center and circulated a petition drive for a recall of the city council members and mayor who supported the project. In the most recent development, the petition has been certified for a recall election of Mayor Brian Pillmore.
“We’re thrilled. This was not an easy task,” said petition organizer Joe Horn.. “We collected 1,704 signatures, and they certified 1,451. We met and exceeded the very highest number.”
KOCO TV News reported the certified petition will be presented to the city council at the Aug. 11 meeting and the council will have 10 days after receiving the certification to order a recall election and set the date.
Residents have filled the city council chambers in the past several months expressing anger at the city’s lack of transparency in selling city land to a data center development.
“That’s not what we’ve had,” said Horn. “This was a hard thing to do, and it was important for the future of Yukon. So, I would love to see somebody that loves Yukon as much as I do.”
Okmulgee
Okmulgee is another city where residents feel there was not enough transparency when county commissioners agreed to allow construction of a Fluidstack data center. reported KJRH TV News.
“Distrust. There’s a lot of distrust,” said one Okmulgee resident when asked about a recent Okmulgee County Commission meeting where the data center was discussed. “I can tell you that there’s just a lot of distrust in general about a data center coming into town. It’s as though there’s a conspiracy. People have determined that.”
It’s something 2 News Oklahoma’s Samson Tamijani has seen in the TV station’s coverage of the data center over the last few months. That lack of trust stems from a public belief that the county wasn’t upfront with people in town about the data center coming to Okmulgee. Klinger says that was addressed in the meeting.
“I think the conclusion people are coming to is that the county commissioners really were not involved in any kind of a meeting or didn’t have any foreknowledge of the Fluidstack data center coming into town,” Klinger said. “So that got dispelled. That’s something that has kind of been lingering.
Tulsa

Hundreds attended a weekend town hall in Tulsa to talk about data centers as organizers said they held the event because more and more Oklahomans are faced with a choice between economic growth and conserving resources. Called “AI Data Centers: Who Pays the Price,” an estimated 400 attended the meeting and many complained they were tired of finding out about data center projects after decisions were made by leaders.
KOTV News on 6 reported the organizers explained their intent was not to stop technology investment but rather to make sure residents have a seat at the table before decisions were made and not afterward. The sponsors of the data center meeting said they also hoped more people started paying closer attention to city council agendas, zoning notices and land records.
Tribal response
Tribal nations across the state have also taken stands against proposed data center developments. The Kickapoo Tribe of Oklahoma is one of the latest. Its Business Committee recently voted to oppose any development of the projects on tribal lands.
“The Tribe is particularly concerned about the potential impacts such facilities could have on local water resources relied upon by Tribal citizens for residential use, agriculture, future community development, and cultural practices. Protecting these resources remains a priority for the Tribe as it plans for future generations,” stated the committee in a Facebook posting.
Committee treasurer Chenille Suke said the decision was made after the tribe had been approached several times for data center development.
“We’ve already gotten so much taken away from us … this is just protecting what we have now,” Suke said in an interview with KOSU Radio.
Other tribes have taken similar action including the Seminole Nation of Oklahoma, which banned facilities from its lands in March.
KOSU Radio also reported that the Caddo Nation is in the midst of gathering information about a possible data center but had not made a decision. The Tribe has met with Colusa Indian Energy to discuss energy sovereignty projects and the possibility of creating a tribal utilities authority.
The company is owned and operated by the Cachil DeHe Band of Wintun Indians of the Colusa Indian Community in California, and works with tribal governments to develop energy infrastructure, including data center services.
Zackeree Kelin, vice president of the Caddo Nation Economic Development Authority, said the tribe is not considering a hyperscale data center during a membership meeting on July 25. Hyperscale facilities are large-scale, designed to house thousands of servers and often used by corporations like Amazon and Google.
“There is absolutely no consideration – categorically – no consideration for a hyperscale data center by the nation. That is not being considered at all in any form or fashion,” Kelin told tribal members. “No one is talking about creating something like a 280-acre industrial park to put a data center on … That is not even being discussed.”
Texas
This week, Texas took another major step over the backlash of the rapid buildout of data centers across Texas as Gov. Greg Abbott announced a moratorium on the approval of data centers until regulatory agencies can audit proposed data centers seeking connection to the state’s electric grid.
The Texas Tribune reported the governor is asking the Public Utility Commission of Texas and the Electric Reliability Council of Texas to ensure data center developers provide information on tax breaks they will receive; power use and generation; water use and cooling operations; efforts to reduce impacts on local communities; and ownership of the facility. Any projects that fail Abbott’s ordered “comprehensive verification and audit” should be denied connection to the grid, the governor said.
“Our top priority is to protect Texans’ safety and quality of life,” Abbott wrote in a statement. “Any project that fails to comply with the requirements set forth by the PUCT and ERCOT, and by state law, must be denied connection to the Texas grid. Simply put, Texans must come first.”