Oklahoma Gas and Electric Company has plans for a $1.75 billion addition to its Horseshoe Lake Power Plant in eastern Oklahoma County in response to growing demands for more electrical power.
The company recently filed a request with the Oklahoma Corporation Commission. (2026-000094) Dustin Gabus, OG&E Senior Communication Specialist said the filing asked for preapproval of a new 755-megawatt combined-cycle natural gas unit.
“In response to growing customer demand for electricity, this was the highest-ranking project in the competitive bidding process that followed the 2026 Integrated Resource Plan. Building the unit will cost less over the long term compared to purchasing power from an external generator, helping keep costs lower for customers,” he explained in a statement to OK Energy Today.
“Excluding taxes and construction financing, the estimated project cost is approximately $1.75 billion. To lower the overall project cost for customers, OG&E also requests approval to use Construction Work in Progress, which is estimated to save customers more than $900 million over the facility’s projected 45-year life.”
Gabus further said the project, known as Horseshoe Lake 15, is expected to enter service in late 2031 and is not part of OG&E’s current rate review.
“The OCC has 180 days to consider the application, and OG&E looks forward to demonstrating why this investment is needed to meet Oklahoma’s growing energy needs,” he added.
In testimony filed with the Corporation Commission, Kimber Shoop, Director of Regulatory Affairs at OG&E, explained the company had a “very robust” Request for Proposal and received 79 bids from 182 entities. He said the company selected 14 winning projects and “is still negotiating with many bidders.”
“These negotiations are complicated by evolving tariff risk, shifting federal policy, supply chain issues, tax credit uncertainty, and high demand for capacity, all of which have made negotiations challenging.”
OG&E’s Director of Major Projects, Christopher B. Lelak emphasized in his testimony that the company was hoping for no delays from public regulators.
“Given recent increases in pricing due to high demand and tariff risk, any delay beyond June 30, 2027 could at minimum lead to a significant price increase for the turbines as well as an unquantifiable impact to schedule.”
He explained that during negotiations with the bidders, the estimated cost of the project increased from $1.699 billion to $1.748 billion.
Should OG&E’s request for pre-approval be allowed, it would mean the utility can recover approved project costs from ratepayers.